Final Construction Update – June 2021

Both Building 1 and Building 2 have received temporary certificates of occupancy (TCO), meaning all residential spaces, the parking garage and all core and shell…

Construction Update for March 2021

Punch list walkthroughs have started on the exterior of the project. All paving work has been completed and received signatures from Denver city inspectors. The…

Construction Update for January 2021

On the exterior of the project, installation of metal panels is complete and the integrated lighting installation is finishing up and ready to be programmed.…

Construction Update for October 2020

On the exterior of the project, installation of metal panels continues at the Arcade and 17th Street passageways to the Paseo. Once installation is complete…

Construction Update for August 2020

On the exterior of the project, brick work is complete on the façade facing the Paseo on Building Area 2C (section of the five-story building…

Construction Update for July 2020

From the exterior, the project is coming more into focus each day and it is clearly taking its final form. The brick masonry is nearing…

Construction Update for March 2020

In Building 1 (10-story building along 16th Street), the brick façade is nearly complete on the upper section at the corner of 16th and Market…

Construction Update for January 2020

Residential interiors are in full production in Building 2 (five-story building along Market and 17th Streets). Trim work and cabinet installation have begun as priming…

Construction Update for November 2019

In October, there was significant activity all across the site. In Building 2 (five-stories, along Market and 17th Streets), drywall installation has begun in earnest…

Construction Update for October 2019

Work on the residential units is progressing. In the low-rise portion of the building, subcontractors are preparing to install HVAC equipment on the roof, and…