Construction Update for March 2021
Punch list walkthroughs have started on the exterior of the project. All paving work has been completed and received signatures from Denver city inspectors. The site construction fencing has been removed, as requested by the city. On the interior of the project initial punch list walkthroughs of all common and
Punch list walkthroughs have started on the exterior of the project. All paving work has been completed and received signatures from Denver city inspectors. The site construction fencing has been removed, as requested by the city.
On the interior of the project initial punch list walkthroughs of all common and back-of-house areas have been completed. The outdoor amenity spaces have not yet been reviewed, but are expected to be complete and ready for owner walkthrough by the end of February.
Final city inspections are scheduled for February and March. Building systems are currently being tested and applicable, specific inspections scheduled.